Project Updates Posted: Playground Safety Surfacing

Wed August 3, 2022

We have been informed that Woodland Estates Park Playground surfacing should be finished by this Friday/Saturday, Aug 5 or Aug 6 with Safety Testing scheduled for Monday 8/8.  Assuming it passes, the playground will open the following day or two (construction fencing to be removed and site tidied up first).

Woodscreek surfacing to start Wednesday 8/10 until finished and Veteran Acres to immediately follow.  Testing is anticipated to follow after a couple days of curing.  The sites will need to be tidied after the fence removal.  SO we anticipate the parks open for play the week of August 20 at the latest.